Structural Steel subcontractors
Structural Steel subcontractor COI requirements
Steel erectors combine every severe construction exposure in one scope: work at height, crane picks over occupied areas, connection design and heavy fabricated property in transit. Their COIs fail on endorsements that most certificate reviewers never ask for: riggers liability for the property they lift, professional coverage for delegated connection design, and completed operations status on a structure that carries the building for decades.
Structural Steel audit
Summit Steel Erectors LLC
Union Yards Mixed-Use Tower
- CGL policy
- GL 5530-2187-41
- AM Best
- A IX
- Carrier
- Copperline Casualty Co.
- DeficientInland marine
No riggers liability evidenced for 38-ton owner equipment pick.
- DeficientCG 22 79
Professional exclusion attached; connection design is delegated to the sub.
- ReviewCG 20 32
Engineer of record not covered as additional insured.
- of steel subcontractor COI packets are deficient on first review
- 78%
- of steel subcontractor COI packets are deficient on first review
- Pikorua Security 2026 Benchmark
- trade rank by defect rate, 7 points above the all-trade average
- 3 of 14
- trade rank by defect rate, 7 points above the all-trade average
- Pikorua Security 2026 Benchmark
- of subcontractor and vendor COIs contain material coverage deficiencies or missing endorsements on first review
- 71%
- of subcontractor and vendor COIs contain material coverage deficiencies or missing endorsements on first review
- AGC Risk Committee Audit
- of COIs claiming additional insured status fail to attach the CG 20 37 completed operations endorsement
- 64%
- of COIs claiming additional insured status fail to attach the CG 20 37 completed operations endorsement
- IRMI Construction Risk Survey
Typical exhibit
Typical steel insurance requirements
- Rules in template
- 16
- Hazard tier
- Severe
| Coverage | Typical limit | What to check |
|---|---|---|
| Commercial general liability (CG 00 01, occurrence) | $2,000,000 each occurrence / $4,000,000 general aggregate | Steel exhibits commonly double the standard CGL tier. Per-project aggregate via CG 25 03. |
| Products-completed operations aggregate | $4,000,000 | Connection failures and deflection claims can surface years after topping out. |
| Business auto liability | $1,000,000 combined single limit | Higher if the erector hauls its own fabricated steel on oversize loads. Hired and non-owned included. |
| Umbrella / excess liability | $10,000,000 each occurrence and aggregate | Crane picks over occupied space or adjacent properties justify $25,000,000 on urban towers. |
| Workers compensation / employer's liability | Statutory / $1,000,000 each accident, $1,000,000 disease each employee, $1,000,000 disease policy limit | Ironworker class codes carry heavy WC rates. Confirm the connector and decking crews are employees or separately insured. |
| Riggers liability | Value of the heaviest single pick or largest piece of owner equipment | Covers damage to property of others while in the erector's care, custody or control during a lift. The CGL excludes this property. |
| Installation floater | Value of fabricated steel in transit and stored on or off site | Fabricated members lost in transit or damaged in laydown are not covered by the CGL. |
| Contractors professional liability | $1,000,000 per claim | When the fabricator's engineer designs connections under delegated design. |
Endorsement checklist
Forms to see attached, not just checked
- CG 20 10Additional insured, ongoing operations
- CG 20 37Additional insured, completed operations
- CG 20 01Primary and noncontributory
- CG 24 04Waiver of subrogation on general liability
- WC 00 03 13Waiver of subrogation on workers compensation
- CA 20 48Designated insured for covered autos liability
- CG 25 03General aggregate applies per project
- CG 20 38Blanket AI for other parties in the contract chain
- CG 20 32Additional insured, engineers, architects or surveyors
Exclusion watchlist
Exclusions that void steel coverage
- Red flag
CG 22 79 Exclusion, Contractors, Professional Liability
Delegated connection design is a professional service. If a connection designed by the fabricator's engineer fails, CG 22 79 can push the loss off the CGL. Require a professional policy or confirm the engineer carries one naming the erector's scope.
Read the CG 22 79 guide - Red flag
Action over / New York Labor Law exclusions
Ironworker falls are the core Scaffold Law exposure. Labor Law 240(1) imposes absolute liability on owners and contractors for gravity-related injuries, and an action over exclusion on the erector's policy leaves the GC absorbing the claim.
- Red flag
Crane and hoisting limitations
Some erector policies exclude crane operations or limit them to cranes the insured owns and operates. If the erector uses a rented crane with an operator, confirm who insures the pick.
- Red flag
CG 21 44 Limitation of Coverage to Designated Premises, Project or Operation
Fabricator-erectors sometimes buy a policy limited to the shop. With CG 21 44 scheduling only the fabrication premises, field erection on your project has no coverage.
Read the CG 21 44 guide
Three policies, not one
A steel erector's exposure does not fit inside a CGL. The CGL handles bodily injury and damage to third-party property, but it excludes property in the insured's care, custody or control. That is exactly where an erector's biggest property exposure sits: owner-furnished equipment it sets, adjacent structures it lifts near and fabricated steel it stores. Riggers liability covers property of others while it is being lifted, moved or set. An installation floater covers the steel itself through transit, storage and erection until acceptance.
Most COI reviews look only at the ACORD 25. Riggers liability and installation floaters are inland marine coverages, typically evidenced on a separate certificate or a policy declaration. Pikorua Security extracts both from the packet and compares the riggers limit against the heaviest pick on the project lift plan you enter in the rule template.
Delegated connection design and the professional gap
On most commercial projects the structural engineer of record delegates connection design to the fabricator, whose engineer stamps the calculations. That is a professional service. If the erector's CGL carries CG 22 79, claims arising from the connection design can be excluded, and the GC is left arguing with two carriers about whether the failure was design or workmanship.
Close the gap in the exhibit: require the fabricator or its connection engineer to carry professional liability, and require CG 20 32 so the engineer of record and the owner's design team are covered as additional insureds when they are not engaged by the erector.
OSHA Subpart R and the jobsite gate
Steel erection is governed by OSHA 29 CFR 1926 Subpart R, which sets requirements for fall protection, connector work and site layout. Insurance cannot replace site safety, but it decides who pays when a fall happens. Because the erector is often on site for a short, intense window, a lapsed policy can expire mid-erection without anyone noticing.
Pikorua Security ties steel compliance to access: if the erector's WC or umbrella expires during erection, the jobsite badge sync suspends new badges for the crew and the PM receives the deficiency notice the same morning.
How to verify a steel sub's COI
A manual review of one COI and its endorsement packet takes 25 to 40 min (CFMA Time Study). These are the six checks, in the order Pikorua Security runs them.
- 1
Match the named insured to the subcontract
Compare the named insured on the ACORD 25 with the legal entity that signed the steel subcontract, including the LLC or Inc. suffix. A trade name or DBA is not the contracting entity, and additional insured coverage follows the policy's named insured.
- 2
Check limits against your steel exhibit
Confirm commercial general liability of $2,000,000 each occurrence / $4,000,000 general aggregate, an umbrella of $10,000,000 that follows form over CGL, auto and employer's liability, and statutory workers compensation. Then confirm riggers liability, installation floater and contractors professional liability are evidenced, because they do not appear on a standard ACORD 25.
- 3
Read the endorsement pages, not the checkboxes
A Y in the ADDL INSD or SUBR WVD column is not an endorsement. Confirm CG 20 10, CG 20 37, CG 20 01, CG 24 04, WC 00 03 13, CA 20 48, CG 25 03, CG 20 38 and CG 20 32 are attached as forms, and that the ongoing and completed operations forms share the same edition date.
- 4
Scan the schedule of forms for steel exclusions
Look for CG 22 79 Exclusion, Contractors, Professional Liability, action over / New York Labor Law exclusions, crane and hoisting limitations and CG 21 44 Limitation of Coverage to Designated Premises, Project or Operation. None of these appear on the certificate; they sit in the declarations schedule of forms and the endorsement pages.
- 5
Check carrier ratings and policy dates
Confirm each carrier is rated A- VII or better by AM Best and that no policy expires before the steel scope and its completed operations period are finished. Set renewal reminders at 60, 30, 15 and 0 days.
- 6
Hold payment and site access until resolved
Keep the steel sub's pay applications and jobsite badges on hold until every finding is resolved, then file the verified packet so it is ready if you ever need to tender a claim.
Try it
Is this steel COI compliant?
What the packet from Summit Steel Erectors LLC shows
Per-project aggregate via CG 25 03
OKMatching editions
OKLimit covers the largest pick
GapTransit, storage and erection
OKAnd no professional policy. Red flag if present.
GapLabor Law 240(1) exposure. Red flag if present.
OK
Switch on = present in the packet. Switch off = missing.
Deficient: 2 findings
Riggers liability evidenced
Damage to lifted property of others is uninsured.
CG 22 79 with delegated connection design
Connection design failures fall outside the CGL.
Pikorua Security would send a deficiency notice to the sub and its broker citing each item, and hold payment until a corrected endorsement arrives.
Questions
Structural Steel COI questions
What is riggers liability and does a steel erector need it?
Why do steel exhibits require higher CGL limits?
Who insures delegated connection design?